Mosul Dam Could Kill 1 Million Iraqis.

Epistemic status: Shallow cause investigation, 10-20 hours of research/​thought distributed lumpily into 2 main periods over 4-5 years. Bat signal, not rigorous.

Acknowledgements: Thank you to Kathy Forth for starting this investigation. She started the draft for a post on this and then handed the project off to me. All mistakes are mine.

Update—There’s some evidence the Iraq government plans to implement one of the permanent fixes? Big if true. See my comment here.

tl;dr—There is a dam 60km north of Mosul city in Iraq that is at chronic risk of collapse. Some call it “The World’s Most Dangerous Dam”.

It was built in the 1980s under the Saddam regime on sediment that contains gypsum deposits, which erode due to the water, creating growing holes under the dam. This requires continuous ‘grouting’, which is filling in the holes with cement and stuff. This is a temporary solution since 1986. One of the dam’s lead engineers has been the lead advocate for dealing with the problem. The Iraq government has not been adequately addressing it. Simulations suggest 500,000 to 1.5 million people could die just from the flooding down the Tigris river all the way to Baghdad, not including famine and a lack of international emergency access due to flooded airports.

Toy Expected Value Calculation: One solution would be to spend $2 billion to finish construction of Badush dam downstream in order to block the floodwaters, which if this saved 1 million lives would come out at $2000/​life saved, better than AMF. Even if that’s likely too optimistic, it’s suggestive, as the likely if as yet unknown existence of more targeted marginal uses of money for readers means this is in my opinion a very promising new cause area worth further investigation, this post being an opener towards further inquiry. I encourage others to do much more detailed expected value calculations, with openminded curiosity.

Operational Status: I am posting this now and might update it after posting because I am encouraged by the spirit of what FTX is currently doing and will submit it to their ideas competition. I am also working on other important stuff and don’t have the attention to optimize this. I would love it if someone who’s not me could take up being a cause champion and spend some time investigating whether this is worth it as a potential EA megaproject. If we could spend $1 million to get governments to spend $1 billion to fix it to save 1 million lives (or something like those orders of magnitude), that would be highly valuable!


From Wikipedia:

A September 2006 report by the United States Army Corps of Engineers noted, “In terms of internal erosion potential of the foundation, Mosul Dam is the most dangerous dam in the world.” The report further outlined a worst-case scenario, in which a sudden collapse of the dam would flood Mosul under 65 feet (20 m) of water and Baghdad, a city of 7 million, to 15 feet (4.6 m), with an estimated death toll of 500,000.[17] A report on 30 October 2007 by the US Special Inspector General for Iraq Reconstruction (SIGIR) said that the dam’s foundations could give way at any moment.[18]

According to The Economist, “One study says that if the dam collapses, Mosul would be submerged within hours. Another warns that half a million Iraqis could be killed by floodwaters, and more than a million forced from their homes. Disease and looting as the floodwaters raced through Baiji, Tikrit, Samarra, and even parts of Baghdad would complete that dreadful scenario.”[19] Nadhir al-Ansari, an engineer involved in the building of the dam who is currently Professor of Engineering at the Luleå University of Technology, Sweden, said that the floodwaters would take four hours to reach Mosul and 45 hours to reach Baghdad, and that more than a million people would be killed if a “good evacuation plan” were not in place.[20]

In 2004, dam manager Abdulkhalik Thanoon Ayoub ordered the dam’s water level, which can reach 330 metres (1,083 ft) above sea level, to have a maximum of 319 metres (1,047 ft), thus reducing the pressure on the structure. Nevertheless, Iraqi officials maintain that the U.S. government is overstating the risk. The Army Corps of Engineers has proposed that the Badush Dam downstream be completed to serve its purpose of obstructing the large wave that would result if the Mosul Dam collapsed. This has been resisted by Iraqi officials, who note that the current plan for the Badush Dam is US$300 million to provide hydroelectric power and help irrigation while the proposed expansion would cost $10 billion.[17]

In 2007, the U.S. Army Corps of Engineers developed and executed a US$27 million plan to help continue maintenance and repairs on the dam in the short-term. The Iraq Government was also recommended a long-term solution that includes the construction of 67 m (220 ft) deep walls around the dam foundation. The project would cost $4 billion and take approximately four to five years to complete.

If you want to learn more I highly recommend the New Yorker piece, “A Bigger Problem Than ISIS”, which is the most in-depth reporting on the topic.

There’s more links in a list below.

According to a report by Ansari and Adamo, permanent solutions are:

1. Install Diaphragm Wall through the Mosul Dam which should extend deep

into the foundation below the lowest gypsum/​anhydrites (GB0) layer. Such

solution has never been used in the world before in a dam site (250m depth).

Comprehensive evaluation, testing, and geotechnical assessment will be required

to prove the viability and effectiveness of this method for Mosul Dam. Such

diaphragm will be the deepest in the world and it will introduce risks associated

with the required depth and complex foundation conditions. In addition, there

would be complex issues associated with contact with bottom outlets and power

tunnels and the length and depth of the Diaphragm Wall in both the left and right

abutments, particularly the left abutment where the Diaphragm Wall may need to

extend for kilometers beyond the spillway, saddle dam, and fuse plug. The

extension in the right side must also be studied carefully taking into consideration

the results of the hydrological numerical model that was done previously. Total

cost must be given considerable considerations. Although it may be possible to

construct the diaphragm wall, it may not fully solve the problems with Mosul

Dam.

2. Complete Construction of Badush Dam- The downstream Badush Dam could

potentially be completed to prevent widespread disaster from the failure of Mosul

Dam. It is understood that Badush Dam was 30-40 percent complete when

construction was stopped in the late 1990’s. Because of question about the

foundation of Badush Dam, this issue should be considered and the likelihood of

gypsum and anhydrite at depth beneath the dam should be considered in the

evaluation. It is likely that the design of Badush Dam should be modified before

construction begins with consideration of diaphragm wall and other design

changes, the cost to construct the Badush Dam would need to be revised

accordingly.

3.” Hybrid Approach” – The safest alternative may be a “hybrid” approach with

utilization of both Mosul Dam and Badush Dam for a period of time, transitioning

the Badush Dam serving as the long term solution. For example, the Badush Dam

could serve for a period of time as a back up in the event of failure of Mosul Dam.

This would essentially mean that the Badush Dam reservoir stays nearly empty for

this period of time to allow enough storage to retain the Mosul reservoir if the

Mosul Dam fails. This would allow the Al Jazera and other irrigation and water

supply systems to rebuild for change in water elevations. Not waiting for failure of

Mosul Dam to fill Badush Dam reservoir and the ensuing issues and risks that

would result, Badush Dam could be completed and the Mosul Reservoir could be

released into Badush Reservoir in a controlled manner. Following that, Mosul

Dam could be decommissioned with an engineered breach to allow the new

Badush Dam to hold the new reservoir.

A diaphragm wall would purportedly cost $3 billion, and completing Badush dam would cost anywhere between $2-10 billion.

There are likely/​definitely other (marginal) solutions that could be more cost-effective from a marginal effective altruist perspective.

I don’t know what a tractable push here on our part would look like besides two main areas I would guess:

  • Doing advocacy/​lobbying governments or other large actors to fund a permanent solution. This is likely fragile, possibly totally unrealistic, but if someone investigated it we could determine if it’s viable.

  • Incrementalist solutions such as improving evacuation capability, emergency food stocks, etc. Maybe we could save 10% of lives in case it collapses using a small amount of our resources (and maybe that could be part of an advocacy push too)?


Links/​Resources/​Quotes


Key Actors (List is unfinished, I’m just getting it out there)

  • Nadhir al-Ansari, professor of water resources and environmental engineering at Lulea University in Sweden and a published expert on the Mosul Dam

    • Foremost advocate for the issue in media

    • Email: nadhir.alansari@ltu.se

    • Phone: +46 (0)920 491858

  • Lulea University Research Team, led by Nadhir al-Ansari

    • Analyzed all data and came up with solutions

  • Nasrat Adamo, former chief engineer of Mosul Dam (contact)

    • Also an advocate.

  • PAFI

    • Peace Ambassadors for Iraq. They convened a symposium about the issue.

    • Update 2022: I think they’re defunct. Their website looks hacked.

  • Issa

    • Another researcher.

  • Azzam Alwash

    • Researcher and environmentalist.

  • TREVI

    • Italian company fixing the dam right now.

  • Dexter Filkins, New Yorker journalist

    • Really good article on it, would know more.

  • Iraq’s Water Resources Ministry

  • U.S. Army Corps of Engineers

  • U.S. Embassy

  • ?

  • ??

  • ???